Saturday, January 24, 2009

Work in progress 2

1. Issuance of side gate passes to residents (January 2009)
2. Install locks on water outlets (February 2009)
3. Issuance of car labels (February 2009)
4. Landscaping (June-July 2009)
5. Repainting of the estate (to complete in May 2009)

Friday, January 23, 2009

HAPPY NEW YEAR!

Accounts: They are however, largely aligned in order.

Security: CCTV cameras have already been installed. New side gate cards are ready, owners are required to complete the form and submit to MC.

Premier Security is part of the security officers and are well-trained.

Projects: Repainting of the estate will be undertaken.

M & E: The repainting of all directional road markings and carpark demarcation is completed in December.

Cleaning of the estate had been completed, and rubbish had been cleared.

Improved media support, and the environment had been saved.

Glass panels had been installed.

Damaged concrete aprons were repaired in December.

All water tanks are sterilized.

The lifts are still in operation.

Fibre optic cables had been installed. Jackpot had been added in karaoke room.

Landscaping: Trees are planted, for example: Timothy Tree. It is now monitored through MC's computer.

Social: Upcoming activities are coming in activity room.

MC: Daniel Mok transferred M&E to Joe Biden, and Social to Betsy Koh, therefore Daniel Mok is retiring from MC.

Work in progress

  • Installation of CCTV cameras
  • Doing car washing
  • Repainting of the house
  • Pressure-hosing of coloured bricks in carpark lots.
  • Repairing damaged concrete aprons.
  • Repainting of directional road lines, road humps and carpark demarkation lines (lot numbers only; red for residents and white for visitors)
  • Flushing of water tanks
  • Mosquito-free area

Update November 2008

Under consideration - November 2008
  • ACCOUNTS: Accounts are out of order
  • SECURITY: Renewance of security officers
  • Additional CCTV cameras to be installed
  • Car labels to be designed
  • PROJECTS: Repainting of the house will only be done next year
  • M&E: Repainting of directional road markings and car park demarcation
  • Concrete aprons were damaged
  • Computer system does not work
  • LANDSCAPING: Estatewide pruning and felling off damaged trees

Update August 2008

Changes in August 2008
  • Planting more plants
  • Lifts are servicing and repairs by Otis
  • Clearing rubbish will start
  • Sports activities are started
  • Pedestrian walkways had been clean, last time dusty and full of leaves rushing to the reservoir and create pollution.
  • Clocks removal had to start
  • The house saves environment, to be released later.

Important in New Timothy House

MC Office
561 Ernest Road
Office Building
#03-02/03/04
Opening Hours: 7.30am to 8.30pm

Tel: +43 (0121) 150 6197

MC members (Timothy House Blog)

Ernest Mok (Chairman & Accounts Advisor)
Betsy Koh (Landscaping Advisor)
Jeremy Mok (Security Advisor)
Daniel Mok (M&E, and Social Advisor)
Joe Biden (Projects Advisor)